Construction Update: Jardinia
23 Feb, 2026
Forming the Future: Jardinia in Motion
Jardinia, Yeronga
Momentum continues to build at Jardinia as the structure rises with clarity and intent. The final major concrete blade walls and stair shafts – critical vertical elements that anchor the building’s core – are now complete, marking a significant milestone in the project’s evolution.
Levels 2 and 3 are advancing in sequence, with slabs poured and formwork progressing steadily, while ground floor areas transition in preparation for finishes trades. Each stage reflects the coordination, precision and commitment of our site team and valued trade partners.
Looking ahead, completion of the concrete structure remains on track for the end of March. Structural steel for the roof will follow in April, with full roof sheeting scheduled for May – bringing the building closer to its finished form.
Delivered in collaboration with Pradella Property, designed by Wiltshire Stevens Architects, engineered by Inertia Engineering, with visualisation by Nord Studio and sales led by Position Property, Jardinia is a testament to collaborative delivery.